Bunnell Demolition Permits: Utility Caps, FPL Disconnects, and the Six-Month Rule

Short answer: the City of Bunnell has its own Building Department and its own demolition permit application. The back page of that form is a utility checklist: before demolition starts, the contractor or owner must locate the water and sewer taps, cap the sewer line and call the City for an inspection, have Utility Billing shut off the water, cap the water line for a second inspection, and get a City signature confirming the water and sewer steps are done. The permit becomes void if work does not start within six months or stops for six months.

Bright red bathtub-style roll-off dumpster on a dirt lot under a clear blue sky, with hook pockets on the front and other dumpsters at the edges.

This guide is based on the City’s forms page, its demolition application (form dated August 23, 2010), its building permit fee resolution adopted October 14, 2024, its tree and right-of-way forms, and Florida DEP, EPA, and Sunshine 811 pages, all checked on November 11, 2026. Phone numbers printed on older forms can change, so confirm them with City Hall.

City of Bunnell or Flagler County?

Flagler County’s government offices are in Bunnell, and that causes confusion. Flagler County’s Central Permitting office is on East Moody Boulevard in Bunnell, but it handles unincorporated Flagler County (and, as of January 2026, the Town of Beverly Beach), not property inside Bunnell city limits. A Bunnell mailing address can also cover land outside the city. Confirm whether the parcel is inside the City before you choose a form.

The City’s website lists City Hall at 2400 Commerce Parkway, Bunnell, FL 32110, phone 386-437-7500. That is a City number, not a Dependable Demolition number. Building forms are on the City’s Forms page under Community Development.

What the front of the demolition application asks for

The City’s Demolition Permit Application asks for the owner or business name, the parcel ID, the demolition address, the type of proof of ownership, the use of the building, and a description of the work. For the contractor, it asks for a state license or certification number and a City of Bunnell occupational license number, the older term for what the City’s newer forms call a business tax receipt. Both the owner and the contractor sign before a notary.

The front page also sets the clock: the permit becomes null and void if authorized work does not begin within six months, or if work is suspended or abandoned for six months at any time. It also warns that failing to follow Florida’s construction lien law can leave the owner owing subcontractors directly.

The utility checklist on the back

The back of the form lists what must happen before demolition, and the order matters:

  • Locate the water and sewer taps before any demolition work begins.
  • Cap the sewer line and notify the City Utilities Department for an inspection of the cap.
  • Have the water shut off by notifying Utility Billing.
  • Disconnect from the water meter and cap the water line, then notify Utilities for an inspection of that cap.
  • Get the City sign-off in the form’s “Water / Sewer requirements completed” block.
  • Arrange propane or natural gas disconnection with the gas provider.
  • Arrange electric disconnection with Florida Power & Light.

The form prints Utilities Department and Utility Billing phone numbers; call City Hall at 386-437-7500 to confirm the current contacts. The cap inspections are City inspections, so schedule them like any other step rather than leaving them for demolition day. The capping itself is work for a licensed plumber or contractor.

Septic tanks, wells, and asbestos

The form also directs owners to the Florida Department of Health’s Environmental Health office for septic tank and well abandonment procedures. If the property is not on City water and sewer, add that call to the plan early.

For asbestos, the 2010 form points to the “Department of Environmental Regulation” with an out-of-area phone number. That agency name and number are out of date. FDEP’s current Asbestos Program page lists Flagler County in its Northeast District, 904-256-1700, and says the Notice of Renovation or Demolition goes to the district at least 10 working days before projects covered by the federal asbestos rule, which has a narrow residential exemption. The fee is $100 when filed and paid together in the DEP Business Portal, or $200 otherwise. Use the current form page, and leave surveys and abatement to licensed professionals.

How Bunnell figures the permit fee

The City’s building permit fee resolution assigns every project, demolition included, a value equal to the greater of the latest ICC Building Valuation Data or the actual contract price. The fee then comes from a valuation table:

Value of constructionPermit fee
$0 to $1,000$50
$1,001 to $10,000$50 for the first $1,000, plus $6 for each additional $1,000 or portion
$10,001 to $100,000$104 for the first $10,000, plus $5 for each additional $1,000 or portion
$100,001 to $500,000$554 for the first $100,000, plus $3 for each additional $1,000 or portion

For example, a demolition contract of $15,000 works out to $104 plus five additional thousands at $5, or $129. The resolution also adds a $10 technology fee to all permits, lists residential inspections at $40 each, and charges re-inspections at $40, then $50, then $60. Work started before a permit is issued is fined at the same amount as the permit fee, and permits under $100 are not refundable. These are City fees, not the price of demolition.

Trees, rights-of-way, and locates

Removing trees is a separate permit. The City’s tree removal packet asks for a tree survey or site plan marking each tree and how it will be replaced, at least two photos of the property, and proof of ownership, and it says contractors must be current on their business tax receipt. The packet quotes the City’s Land Development Code: oak, magnolia, hickory, pecan, red cedar, and many other species are protected index trees. When fewer than one index tree per 2,500 square feet of lot will remain, replacements are required, at least half of them oak, maple, hickory, sweet gum, elm, or cypress, at a minimum of 2½ inches in caliper and 8 feet tall.

Work in the City right-of-way, such as removing a driveway apron or making a street cut, uses the City’s Right-of-Way Access & Utilization Permit Request, which asks for construction drawings and a traffic plan when applicable. Whether or not the right-of-way is involved, Sunshine 811 needs at least two full business days’ notice before digging.

EPA’s lead and demolition page says its renovation rule covers renovation and partial demolition of pre-1978 housing, not total demolition, but EPA still recommends lead-safe practices.

For a sense of typical costs in the region, see our North Florida demolition cost guide, or read about Dependable Demolition.

Planning a project in Bunnell? Call (855) 713-6280 or email [email protected] to ask whether we can help. Include the street address, what is coming down, and anything you already know about the permit, utilities, or trees on the lot. An inquiry does not reserve a date or start a permit. The ranges below are averages from other online sellers, not a Dependable quote.

What demolition costs around Bunnell

In Bunnell, utility caps and electric disconnects have to be planned before a structure comes down, whether the building is a house or a manufactured home. The averages below are for those teardowns and for 20- and 30-yard roll-offs often used once the caps are in and debris starts to move.

WorkAverage published range
Full house demolition$4–$12 per sq ft, or about $6,500–$22,950 for a typical job
Mobile home demolition, single-wide or typical unit$2,650–$5,000
Mobile home demolition, double-wide$5,000–$8,350
20-yard roll-off dumpster in Northeast Florida$505 average ($449–$550 posted)
30-yard roll-off dumpster in Northeast Florida$585 average ($555–$650 posted)

These figures are averages compiled from other online sellers and cost guides, not a Dependable Demolition quote. Sources: HomeGuide, Redfin, Angi, Angi, Bees Mobile Home Removal, Mobile Home Donation Collaborative, American Rolloffs, VETCANS, 904 Dumpster, and Double D’s Dumpsters.

Dependable gives a firm quote after seeing the site in Bunnell. Call (855) 713-6280 or email [email protected].

Frequently asked questions

Do I get a demolition permit from the City of Bunnell or Flagler County?

If the parcel is inside Bunnell city limits, from the City of Bunnell Building Department. Flagler County Central Permitting, which is also in Bunnell, handles unincorporated parcels.

What has to happen with water and sewer before a Bunnell demolition?

The City’s form says to locate the taps, cap the sewer line and have the City inspect it, have the water shut off, cap the water line for a second inspection, and get the City’s sign-off.

How long is a Bunnell demolition permit good for?

Six months. The permit becomes void if work doesn’t start within six months or is suspended or abandoned for six months.

Does a contractor need a City license in Bunnell?

The demolition form asks for a state license number and a City of Bunnell occupational license number, now called a business tax receipt.

How is the Bunnell permit fee calculated?

On value, using the greater of ICC valuation data or the contract price. A $15,000 job works out to $129 on the City’s table, plus a $10 technology fee and inspection fees.

Where does the asbestos notice go for a Bunnell demolition?

To the Florida Department of Environmental Protection’s Northeast District, at least 10 working days ahead when the federal asbestos rule applies. It costs $100 filed and paid online, or $200 otherwise.

Do I need a separate permit to remove trees in Bunnell?

Yes. The City has a tree removal and land clearing permit, and protected index trees may need to be replaced.

How do I ask Dependable Demolition about a Bunnell project?

Call (855) 713-6280 or email [email protected] with the address and scope to ask whether we can help. The ranges on this page are averages from other online sellers, not a Dependable quote. Dependable gives a firm quote after seeing the site.